240094
| 1 | | North Grace Street Underground Improvements, Final Balancing Change Order No. 3 | Resolution | North Grace Street Underground Improvements, Final Balancing Change Order No. 3
Reflecting an increase of $21,541.26 to the contract with John Neri Construction. The revised contract amount reflects agreed field-measured quantities for contract pay items associated with the water and sewer improvements and supplemental pricing for field work not covered by existing pay items. (DISTRICT #4) | recommended to the Board of Trustees for approval | Pass |
Action details
|
Not available
|
|
240101
| 1 | | FY2024 Asphalt Street Resurfacing Program; FY2024 Concrete Roadway Program | Discussion | FY2024 Asphalt Street Resurfacing Program; FY2024 Concrete Roadway Program
Recommendation for Village streets to be improved. The targeted letting date for this project is April 23, 2024. Please provide a recommendation at your earliest convenience so that plans can be finalized and advertised for bid. | discussed | |