250338
| 1 | | Sidewalk and Curb Improvement Program, Final Balancing Change Order No. 1 | Resolution | Sidewalk and Curb Improvement Program, Final Balancing Change Order No. 1
Reflecting an increase to the contract with Globe Construction, Inc. in the amount of $109,829.19. This increase reflects an increased quantity of material and work that was performed. (DISTRICTS - ALL) | approved | Pass |
Action details
|
Not available
|
250356
| 1 | | FY 2025 Commuter Parking Lots Program | Resolution | FY 2025 Commuter Parking Lots Program
Reflecting an increase to the contract with Chicagoland Paving Contractors, Inc. in the amount of $36,585.00. This represents the addition of a parking lot for 355 E. Parkside Avenue, Sheldon Peck Homestead. The existing parking lot was found to be in advanced failure. (DISTRICTS - ALL) | approved | Pass |
Action details
|
Not available
|