Title:
|
Highland Avenue Sewer Separation, Final Balancing Change Order No. 2
Reflecting an increase to the contract with John Neri Construction Company in the amount of $82,210.30. This Change Order includes field-measured quantities of existing pay items, two new authorized unit prices items and two force amounts. Changes were primarily related to poor soils both on South Chase Avenue and Division Street and a water main break during roadway reconstruction. (DISTRICT #5)
|