Title: Highland Avenue Sewer Separation, Change Order No. 1 Reflecting an increase to the contract with John Neri Construction Company in the amount of $211,472.95. The revised contract amount accounts for field measured quantities of current contract pay items and new authorized unit prices. (DISTRICT #5)
Attachments: 1. 250307 Board Meeting Attachment 9.18.25
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Highland Avenue Sewer Separation, Change Order No. 1

Reflecting an increase to the contract with John Neri Construction Company in the amount of $211,472.95. The revised contract amount accounts for field measured quantities of current contract pay items and new authorized unit prices. (DISTRICT #5)