File #: 250432    Version: 1 Name: 2025 Asphalt Roadway Program, Final Balancing Change Order No. 1
Type: Resolution Status: On Consent Agenda
File created: 12/3/2025 In control: Village Board of Trustees
On agenda: Final action:
Title: 2025 Asphalt Roadway Program, Final Balancing Change Order No. 1 Reflecting a decrease to the contract with Schroeder Asphalt Services in the amount of $26,092.33. This Change Order is intended to adjust the contract quantities and to reflect final measured quantities in the field.
Attachments: 1. 250432 Board Meeting Attachment 1.8.26
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

2025 Asphalt Roadway Program, Final Balancing Change Order No. 1

Reflecting a decrease to the contract with Schroeder Asphalt Services in the amount of $26,092.33. This Change Order is intended to adjust the contract quantities and to reflect final measured quantities in the field.