File #: 230289    Version: 1 Name: Manhole Rehabilitation Program, Change Order #2
Type: Resolution Status: Passed
File created: 8/28/2023 In control: Village Board of Trustees
On agenda: Final action: 9/21/2023
Title: Manhole Rehabilitation Program, Change Order #2 Reflecting a decrease to the contract with Structured Solutions, L.L.C. in the amount of $7,250.56. This decrease represents the final field measured quantities for the pay items within the contract. (DISTRICTS - ALL)
Attachments: 1. 230289 Board Meeting Attachment 9.21.23, 2. R 46-23.pdf, 3. Structured Solutions FY 2023 Manhole Rehab Change Order 2.pdf, 4. Cover Page - 230289.pdf

Title

Manhole Rehabilitation Program, Change Order #2

Reflecting a decrease to the contract with Structured Solutions, L.L.C. in the amount of $7,250.56. This decrease represents the final field measured quantities for the pay items within the contract. (DISTRICTS - ALL)