File #: 120230    Version: 1 Name: Westmore-Meyers Road Sidewalk, Phase 2, Design Engineering
Type: Resolution Status: Passed
File created: 4/23/2012 In control: Village Board of Trustees
On agenda: 5/3/2012 Final action: 5/3/2012
Title: Westmore-Meyers Road Sidewalk, Phase 2, Design Engineering Contract Amendment 1 Amendment No.1 reflecting an increase of $3,753.00 to the design service contract with Baxter & Woodman Consulting Engineers to modify the design of the sidewalks on the west side of Westmore- Meyers Road from Roosevelt Road to Norton Street. (DISTRICT #6)
Attachments: 1. 120230 BOT 5-3-12, 2. 120230Coverpage5-3-12, 3. R 85-12
Title
Westmore-Meyers Road Sidewalk, Phase 2, Design Engineering Contract Amendment 1
Amendment No.1 reflecting an increase of $3,753.00 to the design service contract with Baxter & Woodman Consulting Engineers to modify the design of the sidewalks on the west side of Westmore- Meyers Road from Roosevelt Road to Norton Street.  (DISTRICT #6)
Body
[Enter body here.]